Question: At 16 weeks into a project, you have the information in the table shown below. Answer the following question: a. What are the cost variance,

 At 16 weeks into a project, you have the information in

At 16 weeks into a project, you have the information in the table shown below. Answer the following question: a. What are the cost variance, schedule variance, CPI, and SPI values? b. Have you spent more or less than the baseline? c. For the exist already spent, are you ahead of schedule or behind? d. How much additional money will it cost to finish this project, assuming all work continues at its current pace? e. How much will it cost, total, to complete this project? f. If continued at its current rate, will this project be over budget or under budget? By how much

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!