Question: At X1-0, X2= 30 then what is the stack variables for the following linear programming model maximize Z = 4X1 + $X2 Sublict to: 2X1

At X1-0, X2= 30 then what is the stack variables
At X1-0, X2= 30 then what is the stack variables for the following linear programming model maximize Z = 4X1 + $X2 Sublict to: 2X1 + 2X2 S60 X1 + X2 530 O a. S1-40,52-0 Ob 51-0, 52.0 Oc51-50, 520 Od 51-0, 52-50