Question: At zero direct labor hours in a flexible budget graph, the total budgeted cost line intersects the vertical axis at $ 30000 . At 10000
At zero direct labor hours in a flexible budget graph, the total budgeted cost line intersects the vertical axis at $30000. At 10000 direct labor hours, a horizontal line drawn from the total budgeted cost line intersects the vertical axis at $80000. Fixed and variable costs may be expressed as:
Step by Step Solution
3.43 Rating (153 Votes )
There are 3 Steps involved in it
At zero direct labor hour the total budgeted cost ... View full answer
Get step-by-step solutions from verified subject matter experts