Question: Attached to the second page is the work breakdown structure for the manual assembly of a commercial appliance. It is expected that this current model

Attached to the second page is the work breakdown structure for the manual assembly of a commercial appliance. It is expected that this current model will be produced over the next 5 years. The up-time efficiency at 90%. The repositioning efficiency is 90% and M=1.

4. Using appropriate method of choice balance the line with a production rate of 40 u/hour.

Answer the following:

a) What is the number of stations required?

b) How many workers will be needed?

c) Determine the balance efficiency.

Attached to the second page is the work breakdown structure for the

2. 210S wwwwwwwwwwwwwwwwwwwwwwwwwwwwww wwwwwwwwwwwwwwwwww 33 www.vwwwwwwwwwwwwwww .vevo. wwwwwwwwwwwwwwwwwww... 78 wwwwwwwww wwwwwwwwwwwwwwwwwwwwwwwww GARAL 23 26 wwwwwwwwwwwwwww 433 9. Wwwwww vvvwwwwwwwwwwwwww UAB 03 www 3903 wwwwwwwwww 2$ www.3. . wwwwwwwww wwwwwwwwwwwww S3 ANA SALAS 0.33 wwwwwwwww X93 wwwwwwwwwwwwwwwwww pomococco cargo SAXXUX . So. XXX 82 .23 wwwwwwwwwwwwwww 231 0.8 T R IBE ... . .. .. .. . wwwwwwwwwwwwwwwwwwwwww S... . .... www $8.33 UBUXUS *** R 3 ... $$ ******* * ** 0.9 .. ............ 29 PALLAVOLANAVIMAS 8 OOOOoooo 350 XOXO 333 wwwwwwwwwwww wwwwwwwwwwwwwwwwwwwww 99 SULLAR.... . .8 ULETTER wwwwwww 32 06 333 70.21 $ 93 Coco o coxoxoxo 33 2. 210S wwwwwwwwwwwwwwwwwwwwwwwwwwwwww wwwwwwwwwwwwwwwwww 33 www.vwwwwwwwwwwwwwww .vevo. wwwwwwwwwwwwwwwwwww... 78 wwwwwwwww wwwwwwwwwwwwwwwwwwwwwwwww GARAL 23 26 wwwwwwwwwwwwwww 433 9. Wwwwww vvvwwwwwwwwwwwwww UAB 03 www 3903 wwwwwwwwww 2$ www.3. . wwwwwwwww wwwwwwwwwwwww S3 ANA SALAS 0.33 wwwwwwwww X93 wwwwwwwwwwwwwwwwww pomococco cargo SAXXUX . So. XXX 82 .23 wwwwwwwwwwwwwww 231 0.8 T R IBE ... . .. .. .. . wwwwwwwwwwwwwwwwwwwwww S... . .... www $8.33 UBUXUS *** R 3 ... $$ ******* * ** 0.9 .. ............ 29 PALLAVOLANAVIMAS 8 OOOOoooo 350 XOXO 333 wwwwwwwwwwww wwwwwwwwwwwwwwwwwwwww 99 SULLAR.... . .8 ULETTER wwwwwww 32 06 333 70.21 $ 93 Coco o coxoxoxo 33

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!