Question: Award: 1.00 point MC Qu. 28 (Static) A project manager receives the following information on... A project manager receives the following information on his project:
Award: 1.00 point MC Qu. 28 (Static) A project manager receives the following information on... A project manager receives the following information on his project: PV = 4,500, AC =4,000, EV = 5,000. How well is the project doing in terms of budget? Right on budget 1,000 under budget 1,000 over budget 500 under budget 500 over budget