Question: B 2 . Using the following table, do these tasks [ 3 5 points possible ] : a . Correctly & legibly draw and label
B Using the following table, do these tasks points possible:
a Correctly & legibly draw and label the network diagram including process times
Deduct pts for each missingincorrect: arrows, ovals, activity names, process times
b Complete the table of ES EF LS and LFs deduct ptserror
c Identify the critical path or paths deduct points if incorrect
tableNormal,CrashActivityPredecessor,Time daysCost Time daysCost ANone,BCECADDNone,EADFB
tableActivity,CABCDEFESEFLSLF
CPs