Question: B 2 . Using the following table, do these tasks [ 3 5 points possible ] : a . Correctly & legibly draw and label

B2. Using the following table, do these tasks [35 points possible]:
a. Correctly & legibly draw and label the network diagram including process times
(Deduct 2 pts for each missing/incorrect: arrows, ovals, activity names, process times)
b. Complete the table of ES, EF, LS, and LFs [deduct 2 pts/error]
c. Identify the critical path or paths [deduct 8 points if incorrect]
\table[[,Normal,Crash],[Activity,Predecessor,Time (days),Cost (5),Time (days),Cost (5)],[A,None,2,10,1,20],[B,C,E,4,15,1,35],[C,A.D,4,25,2,40],[D,None,5,20,3,50],[E,A,D,6,30,3,35],[F,B,7,5,4,10]]
\table[[,Activity,C],[,A,B,C,D,E,F],[ES,,,,,,],[EF,,,,,,],[LS,,,,,,],[LF,,,,,,]]
CP(s)
 B2. Using the following table, do these tasks [35 points possible]:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!