Question: Assignment # 2 MGMT 3 0 2 0 Bakersfield Pools is about to work on a project to install a backyard pool and build an
Assignment #
MGMT
Bakersfield Pools is about to work on a project to install a backyard pool and build an accompanying bathhouse. The installation process is fairly well defined. Building the pool involves digging the foundation, pouring concrete, and ordering and installing a filtration system. The bathhouse work involves constructing the bathhouse, installing the additional required plumbing, and installing the necessary electrical work. The process is shown in the table below.
Activity
Description Immediate Predecessors
Duration
A
B
C
D
E
F
G
H
I
J Dig pool foundation
Order filtration system
Receive filtration system
Pour concrete
Install filtration system
Construct bathhouse
Install electrical wiring
Install plumbing
Connect water supply
Test
B
A
C D
F
F
H
E G I
Answer the following questions. Ignore the possibility of crashing until part f
a Draw the network diagram for the project. Calculate early start, early finish, late start, late finish, and slack times.
b Bakersfield Pools works all days a week. The customer wants this pool completed in time for a birthday party in days. Can it be done? Why or why not? Note: this means the entire project must be completed. Crashing is NOT possible at this point.
c The staff member who is in charge of pouring concrete wants to go on a twoweek vacation starting in days. Can Bakersfield Pools let him go when he wants? Why or why not?
d Equipment required to do task E the installation of the filtration system is currently undergoing repairs. Until it is repaired, no work can be done on task E What is the latest day those repairs can be completed by without delaying the project? Give your reasoning.
e BPs regular electrician is on vacation, and a temp has been hired. The temporary electrician is not as productive as the regular electrician. Suppose it takes him days to install the electrical wiring, as opposed to days. Does this delay the project? Supply proof a simple yes or no answer is insufficient.
f See part f on the next page.
Activity Normal
Duration Minimum Duration Crash Cost
$day
A
B
C
D
E
F
G
H
I
J
f The customer for whom the pool and bathhouse are being installed would like the project to be completed as swiftly as possible. As an incentive, the customer has offered to pay Bakersfield Pools an extra $ for each day they can reduce the length of the project. Use the table above for crash cost and minimum duration information. What is the most economic duration of the project? How much extra profit would this generate for BP
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
