Question: B 7 D C A 5 1. Based upon the following diagram and activity durations, write down the Critical Path. (2) 2. Based upon the

B 7 D C A 5 1. Based upon the following diagram
B 7 D C A 5 1. Based upon the following diagram and activity durations, write down the Critical Path. (2) 2. Based upon the following diagram and activity durations, what is the LS and LF of activity E? (2) 3. Based upon the following diagram and activity durations, write down the slacks of all activities. (2)