Question: B, 8 E, 7 A, F,7 H, 6 D, 8 G, 4 The early start time (ES) for job Gis: 13, 19, 21, 25 or

B, 8 E, 7 A, F,7 H, 6 D, 8 G, 4 The early start

B, 8 E, 7 A, F,7 H, 6 D, 8 G, 4 The early start time (ES) for job Gis: 13, 19, 21, 25 or 38? -The late finish time (LF) for job Bis 13, 14, 16, 19, or 22? - The critical path is: -The minimum time required to complete the project is: 23 days, 24 days, 29 days or 31 days? -The slack at activity E is: 0,5, 6, 13 or none