Question: (b) A construction project carries out seven activities as shown below: Activity Dependancy Duration A Initial Activity 5 days B Initial Activity 5 days
(b) A construction project carries out seven activities as shown below: Activity Dependancy Duration A Initial Activity 5 days B Initial Activity 5 days C Depends upon Activity A 5 days D Depends upon Activity B 10 days E Depends upon Activity B 5 days F Depends upon C and D 10 days G Depends upon Activity E 10 days Calculate EST, EFT, LST, LFT, by drawing Network diagram. Also show critical path.