Question: b ) A process is scheduled to run 2 4 hours every weekday across 3 shifts. Each shift gets a 2 0 - minute break.
b A process is scheduled to run hours every weekday across shifts. Each
shift gets a minute break. There is also a minute production meeting at
the start of each shift. The total operation time for part is minute. The
demand for the product is parts per week.
marks
Determine the TAKT time for the process and explain briefly what this means.