Question: b ) A process is scheduled to run 2 4 hours every weekday across 3 shifts. Each shift gets a 2 0 - minute break.

b) A process is scheduled to run 24 hours every weekday across 3 shifts. Each
shift gets a 20-minute break. There is also a 10-minute production meeting at
the start of each shift. The total operation time for 1 part is 0.8 minute. The
demand for the product is 275,000 parts per week.
(15 marks)
Determine the TAKT time for the process and explain briefly what this means.
 b) A process is scheduled to run 24 hours every weekday