Question: b) A small project has 7 activities and the time in days for each activity is given on the table below. Activity Immediate Predecessor Time

b) A small project has 7 activities and the time in days for each activity is given on the table below. Activity Immediate Predecessor Time in Days A . 2 B 3 C .. 4 D A 1 E B 2 F B 5 G C 7 H D, E 2 I F, G 3 J H, I 1 Question Show the logical relationship between the activities in the network diagram and show long will the project take to complete