Question: b . Assume the overhead costs for this project are $ 2 , 5 0 0 / month . Also, a penalty of $ 1

b. Assume the overhead costs for this project are $2,500/month. Also, a penalty of $10,000 is assessed for each month the project is delayed beyond month 25. What is the optimal crashing strategy? What is the net benefit of the optimal crashing strategy? Please describe your crashing strategy step-by-step.
c. What is the optimal project duration? What are the critical paths as a result of your crashing?
 b. Assume the overhead costs for this project are $2,500/month. Also,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!