Question: b) Builder Bug Berhad allocates overhend at RM9 per direct labor hour. Job A45 required 4 allocates boxes of direct materials at a cost of

b) Builder Bug Berhad allocates overhend at RM9 per direct labor hour. Job A45 required 4 allocates boxes of direct materials at a cost of RM30 per box and took employees 20 hours to complete. Employees earn RM15 per hour t labor he per hour. Required Compute the total cost of Job A45. 6 marks)
Step by Step Solution
There are 3 Steps involved in it