Question: B C D E F A , B C DE 1 6 5 1 2 2 6 8 9 3 3 6 1 1 1

B
C
D
E
F
A,B
C
DE
1
6
5
1
2
2
6
8
9
3
3
6
11
17
4
a)
b)
Determine the total expected project completion time.
If Activity C is delayed for 2 days, what is the impact on the project completion time?
Select one:
a)18 days; b) No impact
a)13 days; b)1 days delay in total finish time of the project
a)18 days, b)2 days delay in total finish time of the project
a)13 days, b) No impact