Question: b ) Calculate the Expected Time, the Earliest Expected Completion time ( TE ) , the Latest Expected Completion Time ( TL ) and the
b Calculate the Expected Time, the Earliest Expected Completion time TE the Latest Expected Completion Time TL and the Slack Time. Show critical path. Fill in the answer in Table
tabletableActivityNoETSlack time,Critical pathABCDEF
A project has been defined to contain the following list of activities along with their required times for completion.
Table
tabletableActivityNoActivity,tableImmediatePredecessorstableOptimistiC TimetablePessimisticTimetableRealisticTimeACollect requirement,BAnalyze process,ACDesign processes,ADDesign screen,AETest and document,BFInstall,C D E
Based on the Table
a Construct a Pert chart for the activities above.
b Calculate the Expected Time, the Earliest Expected Completion time TE the Latest Expected Completion Time TL and the Slack Time. Show critical path. Fill in the answer in Table
tabletableActivityNoETSlack time,Critical pathABCDEF
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock