Question: ( B ) Construction of CRITICAL PATH METHOD table [ [ , Activity, table [ [ Duration ] , [ ( days )

(B)
Construction of CRITICAL PATH METHOD
\table[[,Activity,\table[[Duration],[(days)]],ES,EF,LS,LF,TF,FF],[A,Project Initiation,5,0,5,0,5,0,0],[B,UI/UX Design,10,5,15,5,15,0,0],[C,Design Approval,3,15,18,15,18,0,0],[D,Front-end Dev,15,18,33,18,33,0,0],[E,Back-end Dev,20,33,38,33,38,0,0],[F,Integration,5,38,43,38,43,0,0],[G,Unit Testing,7,43,50,43,50,0,0],[H,Integration Testing,5,50,55,50,55,0,0],[I,UAT,2,60,62,60,62,0,0],[J,Prepare Deployment,3,62,65,62,65,0,0],[K,Deploy to Production,5,65,70,65,70,0,0],[L,Monitoring & Support,5,55,60,0,0,,]]
 (B) Construction of CRITICAL PATH METHOD \table[[,Activity,\table[[Duration],[(days)]],ES,EF,LS,LF,TF,FF],[A,Project Initiation,5,0,5,0,5,0,0],[B,UI/UX Design,10,5,15,5,15,0,0],[C,Design Approval,3,15,18,15,18,0,0],[D,Front-end Dev,15,18,33,18,33,0,0],[E,Back-end

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!