Question: An engineering project is modelled by the following activity sheet. Activity Predecessor Duration (Days) ES EF LS LF A - 10 B - 14 C

An engineering project is modelled by the following activity sheet.

Activity

Predecessor

Duration (Days)

ES

EF

LS

LF

A

-

10

B

-

14

C

A

11

D

B

5

E

B

15

F

B

20

G

C, D

8

H

C, D

12

I

G

16

J

E, H

10

K

E, H

21

L

E, H

6

M

I, J

9

N

F, L

12

a- Calculate the early time and late time for each event can start. (i.e. calculate ES, EF, LS, and LF for all events).

b- State the critical path for the project.

c- What is the shortest possible time needed to complete this project?

d- Find the total and free float (or slack) on activities D and F.

An engineering project is modelled by the

An engineering project is modelled by the following activity sheet. + Activity Predecessor ES EF LS LF Duration (Days) 10 14 11 A B C D E F G H I J K A B B B C D C D G E, H E, H E, H I,J F, L 5 15 20 8 12 16 10 21 6 9 12 M N a- Calculate the early time and late time for each event can start. (i.e. calculate ES, EF, LS, and LF for all events). b-State the critical path for the project. C- What is the shortest possible time needed to complete this project? d- Find the total and free float (or slack) on activities D and F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!