Question: b) Determine the project duration to complete the project c) Calculate the Indirect cost of the project if the indirect cost is 4000 per day

b) Determine the project duration to complete the project
c) Calculate the Indirect cost of the project if the indirect cost is 4000 per day
d) Calculate the total cost of the project if the indirect cost is 4000 per day
e) What is the shortest duration to complete this project (you have to uncrash some suitable activities to determine the least project cost )
f) Calculate the new cost of the project if the indirect cost is 4000 per day
A new project will be scheduled based on the information given in Table 1. The following activities of the new project are listed with normal time, crash time and the corresponding costs. Activity Precedent Activity Cost Slope (RM day) A B D E F G H I J A B B D B F C, E, G H I Normal Time (days) 5 10 15 14 12 8 10 4 14 5 Crash Time (days) 4 6 15 14 9 7 7 3 9 5 Normal Crash Cost Cost (RM) (RM) 40,000 42,000 120.000 200.000 62,000 62,000 90,000 90,000 80,000 90,500 70,000 78,000 93,000 123,000 42,000 44,000 210,000 220,000 31,000 31,000 (A) (B (C) (D (E) (F (G) (H) (1) Table 1 Determine the project duration to complete the project. The project duration to complete the project = daysStep by Step Solution
There are 3 Steps involved in it