Question: - B E F G J K L M N 1 11 40 12 40 0 2 Period 3 Forecast 30 40 40 50 40

- B E F G J K L M N 1 11 40 12 40 0 2 Period 3

- B E F G J K L M N 1 11 40 12 40 0 2 Period 3 Forecast 30 40 40 50 40 40 30 40 40 50 Customer 31 35 29 4 Orders 21 17 14 33 11 5 2 Projected 5 Avail. Avail. To 6 Promise 7 MPS 200 200 8 9 2. (a) Given the above Master Schedule, fill in the Projected Available and Available to Promise rows: 10 11 On Hand: 35 Lot Size: 200 12 Demand Time Fence: 2 Planning Time Fence: 10 13 14 15 b) A customer wants an order of 100 in period 4. What can you tell them? 16 c) The customer from part (b) cancels their request, but then says they want 120 in period 5. What do you tell them now? 17