Question: b) Find critical path / paths and project completion time. (You can write to the box below or write to an empty paper and upload

b) Find critical path / paths and project
b) Find critical path / paths and project completion time. (You can write to the box below or write to an empty paper and upload the picture, 10 Points) Activity Predecessor Duration 10 B A 8 A 3 D B 6 E H 2 F DE 25 G 10 H C G 3 - IT 5 J 07 K 1,J 10 L FK 2