Question: b) For the set of tasks given below, do the following: Task Time Predecessors (sec) A 80 -- B 25 A C 35 A D

b) For the set of tasks given below, do the

b) For the set of tasks given below, do the following: Task Time Predecessors (sec) A 80 -- B 25 A C 35 A D 20 B, C E 50 F 70 E G 45 H 25 G 1 15 G J 40 F, H, 1 a) Draw the precedence diagram. (2 marks) b) Determine the cycle time. (2 marks) c) Determine the minimum number of stations needed. (2 marks) d) Assign tasks to workstations based on greatest number of following tasks. Use longest processing time as a tiebreaker. (12 marks) e) Compute the efficiency of the process (2 marks) b) For the set of tasks given below, do the following: Task Time Predecessors (sec) A 80 -- B 25 A C 35 A D 20 B, C E 50 F 70 E G 45 H 25 G 1 15 G J 40 F, H, 1 a) Draw the precedence diagram. (2 marks) b) Determine the cycle time. (2 marks) c) Determine the minimum number of stations needed. (2 marks) d) Assign tasks to workstations based on greatest number of following tasks. Use longest processing time as a tiebreaker. (12 marks) e) Compute the efficiency of the process (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!