Question: B) Lower Control Limit = C) Based on the x chart, the wiring process has been ____ (in control/out of control) The Control limits for
B) Lower Control Limit =
C) Based on the x chart, the wiring process has been ____ (in control/out of control)
The Control limits for the 3-sigma R chart are:
Upper Control Limit =
Lower Control Limit =
Refer to Table S6.1 - Factors for Computing Control Chart Lim its (3 sigma) for this problem. Sampling 4 pieces of precision-cut wire (to be used in computer assembly) every hour for the past 24 hours has produced the following results: Based on the sampling done, the control limits for 3 -sigma x chart are (round all intermediate calculations to three decimal places before proceeding with further calculations): Upper Control Limit (UCL- x ) = inches (round your response to three decimal places). DefinitionStep by Step Solution