Question: B . Minimum Cost Schedule ( 2 5 points ) . Information concerning a project is given in the table below. Activity Normal Time (

B. Minimum Cost Schedule (25 points). Information concerning a project is given in the table below.
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s)
A 5100041200-
B 580032000-
C 26001900 A, B
D 3150022000 B
E 590031200 C, D
F 2130011400 E
G 39003900 E
H 55003900 G
Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 14.
a. What is the projects duration if only normal times are used?
b. What is the minimum-cost schedule?
c. What is the critical path for the minimum-cost schedule?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!