Question: I need help with the mathemathical solving problem. Minimum Cost Schedule ( 2 5 points ) . Information concerning a project is given in the

I need help with the mathemathical solving problem. Minimum Cost Schedule (25 points). Information concerning a project is given
in the table below.
Activity Normal
Time
(days)
Normal
Cost ($)
Crash
Time
(days)
Crash Cost
($)
Immediate
Predecessor(s)
A 5100041200-
B 580032000-
C 26001900 A,B
D 3150022000 B
E 590031200 C,D
F 2130011400 E
G 39003900 E
H 55003900 G
Indirect project costs amount to $250 per day. The company will incur a $100 per
day penalty for each day the project lasts beyond day 14.
a. What is the projects duration if only normal times are used?
b. What is the minimum-cost schedule?
c. What is the critical path for the minimum-cost schedule?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!