Question: I need help with the mathemathical solving problem. Minimum Cost Schedule ( 2 5 points ) . Information concerning a project is given in the
I need help with the mathemathical solving problem. Minimum Cost Schedule points Information concerning a project is given
in the table below.
Activity Normal
Time
days
Normal
Cost $
Crash
Time
days
Crash Cost
$
Immediate
Predecessors
A
B
C AB
D B
E CD
F E
G E
H G
Indirect project costs amount to $ per day. The company will incur a $ per
day penalty for each day the project lasts beyond day
a What is the projects duration if only normal times are used?
b What is the minimumcost schedule?
c What is the critical path for the minimumcost schedule?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
