Question: b) part 2 the total project complation time is ? days. (round your responses two decimal) C) For the given project, the earlist start (ES)

 b) part 2 the total project complation time is ? days.
b) part 2
the total project complation time is ? days. (round your responses two decimal)
C) For the given project, the earlist start (ES) and the earliest finish (EP)
round your responses to two decimal)
Activity | ES |EF
A. ? ?
B. ? ?
C. ? ?
D. ? ?
E. ? ?
F. ? ?
G. ? ?
H. ? ?
I. ? ?
J. ? ?
K. ? ?
activity. |LS |LF
K
J
I
H
G
F
E
D
C
B
A
D) referring to the standard normal table the probality kelly Carpet and tim will finsh the project in 41 days or less is ? ( round your responses to two decimal)

Kelle Carpet and Trim installs carpet in cornmercial offices. Peter Kelee has been very concerned with the amount of tirne it tock to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion fime, and the pessirnistic completion time (all in days) for a new contract are given in the following table: This exercise contains only parts b,c, and d b) Activities on the critical path for the project are

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!