Question: b) The activities that represent the projects critical path are? c) if the time to complete the activities on the critical path is normally distributed,

b) The activities that represent the projects critical path are?
c) if the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 55 days or less = ____ (round to two decimal places)
d) Using the standard normal table, the number of days that would result in 99% probability of completion = ______ (round to two decimal places)
Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: Immediate Predecessor(s) Immediate Predecessor(s) EF G H Activity B D E F G Time (days) a m b 5 5 9 1 2 5 7 7 7 5 9 13 2 8 19 2 3 7 2 6 8 A B, C D D Activity H 1 J K L M N Time (days) a m 5 5 2 7 1 4 8 10 3 5 2 2 6 9 8 10 8 11 8 3 11 J LM a) The expected completion time of the project = days (round your response to two decimal places)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts