Question: Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 5 5 9 - H 4 4 7 E, F B 2
Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 5 5 9 - H 4 4 7 E, F B 2 2 4 - I 3 7 9 G, H C 5 5 5 A J 3 4 7 I D 6 8 11 A K 6 8 12 I E 2 9 19 B, C L 1 6 6 J F 1 4 7 D M 1 2 4 K G 2 7 10 D N 6 7 11 L, M A) The expected completion time of the project = ___ days (round your response to two decimal places). B) The activities that represent the project's critical path are ___________. C) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 53 days or less = ___ (round your response to two decimal places). D) Number of days that would result in 99% probability of completion = ___ days (round your response to two decimal places).
Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 5 5 9 - H 4 4 7 E, F B 2 2 4 - I 3 7 9 G, H C 5 5 5 A J 3 4 7 I D 6 8 11 A K 6 8 12 I E 2 9 19 B, C L 1 6 6 J F 1 4 7 D M 1 2 4 K G 2 7 10 D N 6 7 11 L, M
A) The expected completion time of the project = ___ days (round your response to two decimal places).
B) The activities that represent the project's critical path are ___________.
C) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 53 days or less = ___ (round your response to two decimal places).
D) Number of days that would result in 99% probability of completion = ___ days (round your response to two decimal places).