Question: (b) The job (processing times) and due date are given in table below. Taking into consideration the Jobs Priority Rules, use the four scheduling criteria

(b) The job (processing times) and due date are

(b) The job (processing times) and due date are given in table below. Taking into consideration the Jobs Priority Rules, use the four scheduling criteria to evaluate the scheduling efficiency of the jobs below. Job A . B D E Processing Times(days) 26 10 34 14 38 Job Due Date(days) 34 26 74 62 94 [15 marks] (c) What is the conclusion of your analysis? [5 marks]