Question: b) The total operational time for the complete process = ___ seconds (enter your response as a whole number). c) The theoretical minimum number of

b) The total operational time for the complete process = ___ seconds (enter your response as a whole number).
c) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line= __
(round your response to the immediate higher whole number).
d)
For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be:
| Workstation # | Tasks Assigned to Workstation | |
| 1 | A. | ______ |
| 2 | B | _____ |
| 3 | _____ | |
Were you able to assign all the tasks to the theoretical minimum number of workstations?
No
Yes
Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Rosenberg's goal is to produce 175 PDAs per hour. a) The cycle time for the production of a PDA = seconds (round your response to two decimal places)
Step by Step Solution
There are 3 Steps involved in it