Question: B2.Identify the critical path for the project network Marks allocated to questions are indicated next to the question. The planning department of an electronics firm
B2.Identify the critical path for the project network

Marks allocated to questions are indicated next to the question. The planning department of an electronics firm has set up the activities for developing and production of a new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a ve-day workweek and the project starts on January 4, 2017. Activity Description Activity Activity 1D predecessor time(weeks) 1 Staff None 3 2 Develop market program 1 3 3 Select channels of distribution 1 6 4 Patent 1 12 5 Pilot production 1 4 6 Test market 5 4 7 Ad promotion 2 4 8 Set up for production 4,6 16