Question: Baker entered into a building contract with Able under which Baker agreed to construct a garage on Able's lot for $6,000. Lumber Supply Company supplied

Baker entered into a building contract with Able
Baker entered into a building contract with Able under which Baker agreed to construct a garage on Able's lot for $6,000. Lumber Supply Company supplied the lumber at Baker's request, but when Baker failed to pay for the material within a few weeks after it was supplied, the Company filed a construction lien for $3,000 against Able's property. Lumber Supply Company cannot file a lien against Able's property, because the company is not a subcontractor or workman. True False