Question: Balance an assembly line based on the task analysis below. Indicate the idle time at each station. The cycle time has been set at five
Balance an assembly line based on the task analysis below. Indicate the idle time at each station. The cycle time has been set at five minutes. You do NOT have to show a sequence diagram.
| Task | Estimated Time (Minutes) | Sequence Requirements |
| a | 4 | - |
| b | 1 | a |
| c | 1 | a |
| d | 2 | b |
| e | 5 | c |
| f | 3 | d |
| g | 4 | e |
Step by Step Solution