Question: Balance the assembly line as shown below for (a) a shift output of 100 pieces and (b) a shift outputof 70 pieces. Assume an 8-hour

  • Balance the assembly line as shown below for (a) a shift output of 100 pieces and (b) a shift outputof 70 pieces. Assume an 8-hour shift and use the rule: choose the assignable task with the longestprocessing time. Compute the line efficiency for each case
  • 5 A B D E G Time F H 10 5 K

5 A B D E G Time F H 10 5 K 3