Question: Given the estimated activity times below and the network in Exercise 8 , Activity a m b A 6 . 5 7 . 5 1

Given the estimated activity times below and the network in Exercise 8,
Activity
a
m
b
A
6.5
7.5
14.5
B
8.5
10.5
12.5
C
2.5
3.5
4.5
D
6.5
7.5
8.5
E
5.5
5.5
9.5
F
5.5
7.5
9.5
G
4.5
6.5
8.5
H
2.5
3.5
3.5
what is the probability that the project will be completed within (based on the path with the longest expected time):
21 days?
22 days?
25 days?