Question: Balance the assembly line shown below for (a) a shift output of 50 pieces and (b) a shift output of 30 pieces. Assume an 5-hour
Balance the assembly line shown below for (a) a shift output of 50 pieces and (b) a shift output of 30 pieces. Assume an 5-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case.
Fill in the table below for a shift output of 50 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
| Workstation | Tasks | Total Time | Idle Time |
| 1 | b,e | ? | ? |
| 2 | a,c,f | ? | ? |
| 3 | d,g,i | ? | ? |
| 4 | h,j,k | ? | ? |
| Total | ? | ? |
What is the assembly-line efficiency? Round your answer to one decimal place.
???? %
Fill in the table below for a shift output of 30 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
| Workstation | Tasks | Total Time | Idle Time |
| 1 | b,e,a,c | ? | ? |
| 2 | f,d,g,h,i | ? | ? |
| 3 | j,k | ? | ? |
| Total | ? | ? |
What is the assembly-line efficiency? Round your answer to one decimal place.
???? %