Barkes, Inc., manufactures and sells two products: Product B0and Product B5. Data concerning the expected production of
Fantastic news! We've Found the answer you've been seeking!
Question:
Barkes, Inc., manufactures and sells two products: Product B0and Product B5. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below:
Expected Production | Direct Labor-Hours Per Unit | Total Direct Labor-Hours | ||||||
Product B0 | 400 | 7.0 | 2,800 | |||||
Product B5 | 500 | 4.0 | 2,000 | |||||
Total direct labor-hours | 4,800 | |||||||
The direct labor rate is $22.10 per DLH. The direct materials cost per unit is $288.10 for Product B0 and $118.90 for ProductB5.
The company has an activity-based costing system with the following activity cost pools, activity measures, and expected activity:
Activity Cost Pools | Activity Measures | Estimated Overhead Cost | Expected Activity | ||||
Product B0 | Product B5 | Total | |||||
Labor-related | DLHs | $ | 136,944 | 2,800 | 2,000 | 4,800 | |
Production orders | orders | 64,629 | 500 | 400 | 900 | ||
Order size | MHs | 588,294 | 3,300 | 3,000 | 6,300 | ||
$ | 789,867 | ||||||
The activity rate for the Order Size activity cost pool underactivity-based costing is closest to:
Multiple Choice
a. $164.56 per MH
b. $68.47 per MH
c. $93.38 per MH
d. $65.82 per MH