Question: Barring a change in project scope and given a Cost Performance Index (CPI) that is less than 1, the most reasonable inference to draw is
Barring a change in project scope and given a Cost Performance Index (CPI) that is less than 1, the most reasonable inference to draw is that: The project will likely finish earlier than planned. The