Question: Barring a change in project scope and given a Schedule Performance Index ( SPI ) that is greater than 1 , the most reasonable inference
Barring a change in project scope and given a Schedule Performance Index SPI that is greater than the most reasonable inference to draw is that:
The project is on time and on budget.
The project is behind schedule.
The project is below budget.
The project is ahead of schedule.
The project is over budget.