Question: Based on a standard network method for calculation and using days as the calendar period for scheduling a task was calculated to have an ES

Based on a standard network method for calculation and using days as the calendar period for scheduling a task was calculated to have an ES of 24. The project that is being worked on 7 days each week for up to a 28 days and work began (started) on the first day of the month (For example February 1). On which day of the month (the numbered day) would work on this task begin?