Question: Based on research, these are three practical steps for successful teamwork to emerge (choose the BEST answer according to class readings): Select one: a. Define
- Based on research, these are three practical steps for successful teamwork to emerge (choose the BEST answer according to class readings):
Select one:
a. Define roles and responsibilities; clarify goals and expectations; reward achievement
b. Make the project team tangible; reward good behavior; develop a personal touch
c. Support the team; clarify stakeholder requirements; reward behavior
d. Risk prioritization management
e. Organize the team; clarify scope, time and budget; celebrate successes
- In activity scheduling this is the most common type of logical sequencing between tasks.
Select one:
a. Finish to start
b. Parallel sequencing
c. Start to finish
d. Start to start
- In project scheduling the two most common methods for constructing activity networks involve Activity on Node and Activity on _______.
Select one:
a. Arrow
b. Path
c. Point
d. Task
- In project scheduling this is a network analysis technique used to determine the amount of float on various logical network paths in the schedule, and also determine the minimum total project duration.
Select one:
a. Backward / Forward path estimation
b. Critical path method
c. Path network costing
d. Program Evaluation and Review Technique (PERT)
- In project scheduling this term refers to the amount of time an activity may be delayed from its early start without delaying the project finish date.
Select one:
a. Critical path delay
b. Node delay
c. Float
d. Burst activity