Question: Based on the activity on node diagram and the table below, use the PERT method to determine the probability of completing the project in 19

Based on the activity on node diagram and the
Based on the activity on node diagram and the
Based on the activity on node diagram and the table below, use the PERT method to determine the probability of completing the project in 19 days. Select the probability that is closest to your retul The critical path B, 5 E.7 A F, 3 G3 H.4 Opisto day Mostly made AY toys A, 2 C, 4 F, 3 G3 H,4 D. 7 Activity Optimistic time (a) [days Most likely time (m) Pessimistic time (b) [days) [days B 1 4 D 5 T 2 5 4 7 7 3 10NM CADW F 2 N-N H 2 4 376 0.83 O2 58 6.65