Question: Question 2 4 ( 1 5 points ) Based on the activity on node diagram and the table below, use the PERT method to determine

Question 24(15 points)
Based on the activity on node diagram and the table below, use the PERT method to determine the probability of completing the project in 19 days. Select the probability that is closest to your result.
\table[[Activity,\table[[Optimistic time (a)]],\table[[Most likely time (m)]],\table[[Pessimistic time (b)]]],[A,1,2,3],[B,4,5,9],[C,1,4,7],[D,5,7,9],[E,5,7,9],[F,2,3,4],[G,1,3,5],[H,2,4,6]]
a)65
b)83
c)58
d)76