Question: Based on the activity on node diagram for a project shown below, select the correct critical path of the project. A ( 3 ) +

Based on the activity on node diagram for a project shown below, select the correct
critical path of the project.
A(3)+ B(2)+ D(6)+ F(5)+ G(7)=23
A(3)+ C(4)+ D(6)+ F(5)+ G(7)=25
A(3)+ C(4)+ E(4)+ F(5)+ G(7)=23
A(3)+ C(4)+ E(4)+ G(7)=18