Question: Based on the below information construct an activity on arrow network (AOA) diagram and find the critical path. Tasks Precedence Time a - 6 weeks
Based on the below information construct an activity on arrow network (AOA) diagram and find the critical path.
Tasks Precedence Time
a - 6 weeks
b - 4 weeks
c - 3 weeks
d a 4 weeks
e b 3 weeks
f b 2 weeks
g c 3 weeks
h d,e 2 weeks
i f 1 week
j g,i 2 weeks