Question: Network scheduling process for AOA 1. Draw diagram? 2. Forward path to determine activities early-start times? 3. Backward path to determine activities late-finish times? 4.
Network scheduling process for AOA
1. Draw diagram?
2. Forward path to determine activities early-start times?
3. Backward path to determine activities late-finish times?
4. Float calculations?
5. Identifying critical activities?
| Tasks | Precedence | Time |
| a | - | 6 Weeks |
| b | - | 4 Weeks |
| c | a | 3 Weeks |
| d | b | 4 Weeks |
| e | b | 3 Weeks |
| f | - | 10 Weeks |
| g | e, f | 3 Weeks |
| h | c, d | 2 Weeks |