Question: Based on the below table of project activities, determine the activities on the critical path and the estimated slack for each activity. Activity Time (

Based on the below table of project activities, determine the activities on the critical path and the estimated slack for each activity.
Activity Time (Days) Precedence Relationship Cost ($)
A 2 None (start)100
B 30 A 2100
C 10 A 800
D 7 A 1750
E 1 None (start)200
F 1 E 300
G 4 F 1000
H 6 F 1500
I 1 F 200
J 3 I 900
K 5 I 1000
L 1 I, D 200
M 3 E 210
N 1 K, L 200
O 1 H,J 240
P 4 N, O 2000
Q 1 C 100
R 1 G, P 100
S 4 R, Q 1700
T 7 B, S 2400
U 1 M, S 100
V 2 T, U 1000