Question: Based on the below table of project activities, determine the activities on the critical path and the estimated slack for each activity. Activity Time (

Based on the below table of project activities, determine the activities on the critical path and the estimated slack for each activity.
Activity Time (Days) Precedence Relationship Cost ($)
A 2 None (start)100
B 30 A 2100
C 10 A 800
D 7 A 1750
E 1 None (start)200
F 1 E 300
G 4 F 1000
H 6 F 1500
I 1 F 200
J 3 I 900
K 5 I 1000
L 1 I, D 200
M 3 E 210
N 1 K, L 200
O 1 H,J 240
P 4 N, O 2000
Q 1 C 100
R 1 G, P 100
S 4 R, Q 1700
T 7 B, S 2400
U 1 M, S 100
V 2 T, U 1000\table[[Activity,Time (Days),Precedence Relationship,Cost ($)],[A,2,None (start),100],[B,30,A,2100],[C,10,A,800],[D,7,A,1750],[E,1,None (start),200],[F,1,E,300],[G,4,F,1000],[H,6,F,1500],[I,1,F,200],[J,3,I,900],[K,5,I,1000],[L,1,I, D,200],[M,3,E,210],[N,1,K, L,200],[O,1,H,J,240],[P,4,N, O,2000],[Q,1,C,100],[R,1,G, P,100],[S,4,R, Q,1700],[T,7,B, S,2400],[U,1,M, S,100],[V,2,T, U,1000]]
 Based on the below table of project activities, determine the activities

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!