Question: Based on the BOM and the MPS for end item A shown below, complete the MRP schedule for items A, C, D, and E. MPS
Based on the BOM and the MPS for end item A shown below, complete the MRP schedule for items A, C, D, and E.

MPS
B (1) 3 weeks E (2) 1 week C (4) 1 week F (6) 2 weeks A 1 week E (4) 1 week D (2) 2 weeks G (4) 1 week H (1) 3 weeks Item A Item 1 60 Lot size rule Safety stock Beginning inventory 2 20 3 50 A LAL 0 0 4 5 120 100 C L4L 0 0 6 50 D L4L 0 0 7 80 8 40 E Multiples FOQ = 500 100 300
Step by Step Solution
3.41 Rating (160 Votes )
There are 3 Steps involved in it
Item A Safety stock 0 Beginning inventory 0 L4L 0 1 2 3 4 5 6 7 8 Gross requirements 60 20 50 120 10... View full answer