Question: Based on the BOM shown below, What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.) Based on

Based on the BOM shown below,

What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.)

Based on the BOM shown below, What is the

Based on the BOM shown below, 4 weeks B (2) 3.2 weeks C (2) 3.2 weeks D (2) 4 weeks D(3) 4 weeks G(5) 2 weeks F(2) 3 weeks E (4) F(3) 3 weeks E(4) 2 weeks 2 weeks F(3) 3 weeks What is the cumulative lead time for end Item A? (Round your answer to 1 decimal place.) Cumulative lead time weeks